Boots on Site: What should your Architect do during construction?

Planning approval is a milestone, not the finish line. Many clients assume an architect's job ends once the drawings are approved and a builder is appointed. In reality, some of our most valuable work happens once the diggers, hard hats and hi-vis’s arrive on site and the kettle in the site cabin gets its first outing

RIBA Stage 05 of the RIBA plan of works is where everything designed on paper starts to become a reality. Initially taking shape in the form of bricks, steel, glass, timber and more often than not – a lot of mud. At Peak Architects we call this phase the Construction and On-Site Client Advisory role.

Before work starts

Before anyone breaks ground, your architect should engage in pre-start meeting with the client, contractor and wider design team. A programme is agreed, responsibilities outlined, regular site meetings scheduled and how queries and changes are recorded is established.

Site visits and quality inspections

As much as we love our office environment (particularly in winter) we also enjoy getting out in the fresh British weather and seeing our designs come to life.

Regular site visits are scheduled on either a fortnightly or monthly basis, timed not just to get us out the office, but to ensure we have in-person visibility of key stages of the build: foundations, frame, roof, windows and finishes to name a few. On each visit we check the work matches the approved drawings and specification, from workmanship and materials to the details that make a design special. Problems identified early are far cheaper and more often than not quicker to fix than those raised later on in the build.

Our inspections don't replace the contractor's responsibility for quality or contract administrators’/project managers role. We are an extra, independent pair of eyes protecting the design and your investment.

Solving problems on site

Construction is not a straightforward activity, no matter how much you plan and programme the works.  Every project raises questions once shovels start hitting the ground, from a dimension to confirm to a product to approve. Your architect should respond quickly to queries raised, because a slow answer can hold up the whole site. Bigger issues can also arise: unexpected ground conditions, hidden structure in an existing building, or a product that becomes unavailable due to supply chain issues out of the project teams control. Therefore having an Architect appointed at this stage who can think quick, respond quicker and provide clear directions to solve problems without losing the design intent is crucial for keeping a project moving forward.

Compliance and building safety

Your Architect should work closely with Building Control, answering queries and making sure the right information is ready and inspections are co-ordinated with the contractor. The introduction of the Building Safety Act has raised the bar on compliance, and recording change throughout the construction process. Your architect should make sure design information, including changes made on site, is checked, recorded and communicated to building control in a timely manner – ensuring that there are no unwanted surprises when it comes to building control issuing completion certificate for the project.

Domestic homes: what homeowners can expect

A bespoke new home or large extension is often a once-in-a-lifetime project. Having recently undertaken a Home renovation and extension myself, I can definitely understand the excitement, nerves and stress, not to mention a few weeks of washing up in the bathroom sink.

With our Domestic Homes Clients, your architect should act as your advocate on site.

  • Translating the technical side. Your architect should explain what is happening and what decisions are needed and when they are needed, so you can choose with confidence and in a timely manner.
  • Choices made on site. Brick samples, window finishes, joinery and lighting are often decided during the build. Your architect should help you review samples, so the finished house feels as you imagined.
  • Living with the build. If you stay at home during an extension, your architect should look to help you plan phasing and access with the contractor to keep disruption down.
  • Protecting the details. Frameless glazing, crisp roof edges and level thresholds are often the first things quietly changed on site. Your Architect should look to make sure they are built as designed.

 Commercial projects: working across sectors

Our commercial work spans residential, care and senior living, education, leisure and hospitality, retail, industrial and distribution, workspace and heritage and facade remediation. RIBA 5 here is larger, more formal and driven by tight deadlines and commerciality, so we provide structured reporting on progress, risk, planning and building regulation compliance.

Your architects role depends on the procurement route. On a traditional contract your architect usually acts as Project Lead. On design and build, your architect may be the client's design advisor or be novated to the contractor to complete the design. In most scenarios your architect will be the Lead Designer.

Each sector brings its own challenges:

  • Care, education and hospitality
    • buildings often stay open, so phasing and safe segregation are essential. The designs focus on what service can be provided in the space, how the spaces interact with each other and efficiencies with how people move around the buildings.
  • Heritage
    • historic fabric needs close supervision, specialist trades and dialogue with conservation officers. Ensuring that the heritage of the building is protected at all times.
  • Passivhaus
    • performance depends on workmanship, so your architect should be reviewing critical details and support airtightness testing.
  • Industrial and distribution
    • fast-track programmes need quick decisions and close coordination with specialist contractors. If your project doesn’t have an end user at the point of initial design, they might come forward during construction. Your architect needs to ensure flexibility within the project to cater for a variety of end user needs.

 

Why keep your architect on site?

It can be tempting to save fees by ending your architect's role after planning or tender. But construction is where most money is spent and equally most can go wrong. Keeping your architect involved means the design you approved is the one that gets built, problems are caught early, helping to control cost and you have an independent expert on your side to guide you through the challenges that construction brings. Whether you’re thinking about working with Peak Architects or another practice we would always recommend having your architect work with you throughout the construction phase and we’re not just saying that because we are architects.

Want to talk about a Project?

Whether you are planning a bespoke home, a large extension or a commercial scheme, our practice can support you throughout the process from first sketch to handover. Book a Call with one of our team members using our online booking system and we will advise if we can assist you with your project.